Leslie Dan Pharmacy Building, University of Toronto Norman Foster, Design Consultant Moffat + Kinoshita Architects Toronto, Ontario
|
Project Information: | |
The building combines AESS tube steel for the pod construction with structural steel for the main floor supports. The lower pod will be suspended. Architects:
Moffat and Kinoshita, Toronto |
Project Images: | |
View
of the lower pod, complete. This pod will be lifted some 3.5 metres off
of the ground. |
View
of pod pieces on site ready for erection. |
Lifting
one of the pod pieces. |
Pod
pieces lifted and carefully positioned by the crane operator. |
Ironworkers
accept the pod piece and carefully position and bolt it in place. |
Lifting
another pod piece. |
Aligning
the pod piece prior to connection. |
Steel
floor framing in progress over the large ground floor atrium space that
will contain the pods. |
View
of 50 tonne truss that will be lifted into place on September 15, 2004. images of the erection! |
Ironworkers
prepare to connect another floor member. |
Preparing
the connection prior to the lift. |
Floor
member being hoisted by the crane into position. |
Gently
pulling the beam into the connection takes great skill and care on the
part of both the crane operator as welll as, teamwork on the part of the
ironworkers. |
The crane maintains the beam in position until the ironworker has completed bolting the connection. |
These images are for educational use only and may not be reproduced commercially without written permission. tboake@sympatico.ca |